Capital Project

September 18, 2020

Please use this link to view an update on the Capital Project that was made
to our Facilities Committee on 9.16.20


This link will show you drone video footage from our campus.


August 12, 2020

Please view this brief slideshow to view the progress of work being done. 


July 9, 2020

A groundbreaking ceremony was held today on the Rondout Valley Football Field to signify the beginning of Phase 1 of our Capital Construction Project. Among other things, Phase 1 will provide our main campus with a multi-purpose artificial athletic field, new track, field lighting, new score board, and new grandstands and press box. Repairs to the septic fields and replacement doors on campus are also a part of Phase 1 on our main campus.

Today's groundbreaking ceremony was attended by members of our Board of Education, District Administrators, Assemblyman Cahill's Office, District Coaches, and Student Athletes.

Groundbreaking
Groundbreaking

Groundbreaking




June 8, 2020
Please view these brief slideshows to view work that is beginning
soon in our buildings. 







November 15, 2019
New Grandstands, Press Box, & Athletic Field

field
front

rear

side

Athletic Fields

 October 1, 2019
Click here to view a downloadable pdf of the Phase 1
Construction, currently in the design state


Capital Construction Project

Phase 1
Construction Summer 2020


High School
Turf Athletic Field (Co-op)
New Track (Coating Co-op)
Field Lighting (Co-op)
New Score Board (Co-op) {pictured below)
New Grandstands and Press Box
Fencing around track
New asphalt walkway around track
Repair Septic Fields (Serves HS, MS, DO)
Repair Forced Main
Replace 500 Wing Doors and hardware with Shelter In Place style hardware
Replace all interior damaged doors
Replace Stage Doors
(Proposed Scoreboard seen below)
Proposed Scoreboard


Marbletown Elementary School

Replace Roof and Skylights
Install New Roof Ladders
Add Lightning protection to chimney
Replace building carpeting all areas
Replace drainage piping to kitchen wash sink
Replace building flooring all areas including non-terrazzo hallways
Remove asbestos in plumbing pipe chase below grade
Remove VAT and base and install new VCT and rubber base in all classrooms


Kerhonkson Elementary School

Renovate gym lobby entrance
2nd floor flooring asbestos abatement & installation of new VCT flooring
Replace Carpet in Library - Computer Lab - Book Room - Room 143
Replace Roof
Replace Gym Flooring
Enclose stairs to 2nd floor
Install exhaust fans for rooms on the second floor



December 11, 2018

Capital Project Vote
Vote Date: December 11th, 2018

The Capital Project Vote was passed by RVCSD voters. 
Yes - 685
No - 642


October 23, 2018
Please note that the video is a large file and may take a moment to load.